City Hall·Topsham 2026-11-04 Tedford Road Design Meeting
Topsham Town Manager and Engineers Present Design Plan for Tedford Road Reconstruction
Town officials and engineers presented a comprehensive design plan to reconstruct Tedford Road, which includes rebuilding the road surface, adding a sidewalk on the west side, and installing new drainage systems. The project is estimated to cost approximately two million dollars, with funding coming from town reserves and a capital improvement budget, and is tentatively scheduled to begin in the summer of 2027.
Key points
- The project scope includes widening the road to accommodate two 11-foot travel lanes, a 5-foot sidewalk on the west side, and a gravel shoulder on the east side.
- The Town of Topsham and the Brunswick Water District will share costs, with the water district paying for the extension of the water main to the end of the road.
- Residents expressed significant concern regarding the potential removal of large pine trees and the safety of their homes from falling branches during the box cut reconstruction.
- The Brunswick Post Office requires all mailboxes to be moved to the east side of the road to allow for safe delivery alongside the new sidewalk.
- Public comment highlighted concerns about stormwater runoff affecting nearby farms and the lack of treatment for water draining from the new catch basins.
- The state Department of Transportation has agreed to pay for the removal and replacement of the railroad tracks at the crossing, though the lease for car storage on the tracks remains uncertain.
Next steps
- The engineering firm will conduct a final site survey next week to verify locations and drainage points before submitting the design for bid.
- The project will proceed to the bidding phase after the design is finalized and approved by the Select Board.
- Residents with specific concerns about trees or property impacts are encouraged to speak directly with the engineers during the open discussion portion of the meeting.
Where this came from
Town of Topsham (YouTube)
The summary and transcript were made by software from the public meeting video, with names checked against the official roster, then reviewed before publishing.
Watch the meeting ↗The summary and transcript were made by software from the public meeting video, with names checked against the official roster, then reviewed before publishing.