City Hall·Hollis Planning Board Meeting
Hollis Planning Board Reviews Cistern Standards and Data Center Moratorium
The Hollis Planning Board discussed proposed updates to cistern standards for subdivisions, debating the reliability of aging tanks versus requiring individual sprinkler systems. The board also voted to hold a public hearing on a select board data center moratorium and recommended lowering the size threshold from 25,000 to 2,500 square feet.
Key points
- Board members debated whether to require individual sprinkler systems in subdivisions to replace failing cisterns or to keep cisterns with stricter maintenance and reserve fund requirements.
- A motion was passed to hold a public hearing on the data center moratorium on November 17, 2026, replacing the originally scheduled November 11 date.
- The planning board voted to recommend to the select board that the data center moratorium apply to facilities of 2,500 square feet or larger instead of the proposed 25,000 square feet.
- The board unanimously recommended that a planning board member be included on the select board committee reviewing data center regulations.
- Public comment was waived due to the absence of attendees, though residents were invited to speak at the upcoming hearing.
Next steps
- The planning board will hold a public hearing on the data center moratorium on November 17, 2026, at 7:00 p.m.
- The board will submit a recommendation to the select board to reduce the data center moratorium size threshold to 2,500 square feet.
- The board will recommend that a planning board member join the select board committee reviewing data center ordinances.
Where this came from
Hollis via SRCM (YouTube)
The summary and transcript were made by software from the public meeting video, with names checked against the official roster, then reviewed before publishing.
Watch the meeting ↗The summary and transcript were made by software from the public meeting video, with names checked against the official roster, then reviewed before publishing.