Speakers labeled via automated voice-based diarization + AI name-matching against the city's official roster. Automated transcription can still mis-hear a name during fast speech (e.g. a rapid roll-call vote) -- clear near-misses are auto-corrected, but this is not manually verified line-by-line. Treat names as a strong best guess, not an official record. Home addresses that residents give are left out of this page.
[0:08] Speaker A (unidentified): Good evening. Welcome to the November 10th Brunswick Planning Board meeting. Thank you all for being here. I'll introduce members of the board and staff who are present tonight. On my far right, Rob Burgess, Planning Board Vice Chair. Next to Rob, Steve Walker. Next to Steve, Chris Baldwin. On my near left, Allison Harris, and doing solo duty tonight, Matt James, our land use planner and director of planning and development and assistant director of planning and development for tonight. We have one case before us, case number 2650, 11 Pegasus Street, multi-tenant building. And we're glad to see Jim Howard and Kurt Neufeld come on up. Have Kurt, let me do a completeness motion first, and then I'd like a motion that the staff review committee concurs with staff's conclusion that the basic sketch plan major development review application materials have been submitted and that the application is complete such that the board may proceed with substantive review of the application and identification of any further information required from the applicant. Motion by Steve. Second by Chris. All those in favor, unanimous of the board members present. Well, flaky, huh?
[1:52] Speaker B (unidentified): okay good evening kurt newfeld with priority real estate group representing the project tonight. This is a kind of an unusual project in that we're permitting it on spec. We won't build it on spec but it's a fine piece of dirt as we say in the business and like to go ahead and get permitted because this is a demand out there at Brunswick Landing that just we don't have enough of these types of buildings. So next slide. This is a fairly small site, 1.85 acres, right at the corner of Pegasus and Katahdin. You'll see in the package there was a little discussion about Schooner Drive. The Schooner Drive isn't a drive, at least as far as this parcel is concerned. Back when the Navy turned things over, of course, they had a lot of boring names like First Street and A Street, and it fell to merit to rename paved areas with names that would meet the e911 requirements, and so a lot of them got renamed. Some of them remained as easements or rights away that stayed with the land. Some of them, obviously like Admiral Fitch, was as bigger. So in this area, Schooner Drive ran from Line Drive and came out to Pegasus, and then at some point when somebody bought the lot Right now that has the two buildings on it that landowner requested. The piece that went to Pegasus go away, and so Schooner Drive stopped just short of the lot we're looking at, and I can point that out. So right now, it's just a bunch of pavement on our land, and I worked with Tyler, and we gave it Pegasus address of 11 Pegasus. Okay, so all the utilities are available from the rights-of-way. This parcel will be rolled into a main dot traffic movement permit that's already underway for priority park so that's pending and a stormwater law permit I should have revised that this pushed the projects that priority real estate group has done over a threshold so now we're doing a rolling everything into a site location Development Act permit with the DEP so we've already had our pre-application meetings I had the public informational meeting Monday so that process is underway. Next slide. Please so the existing conditions Stark systems is at the top of the page Pegasus running on the bottom and Katahdin on the left you can see all the hatched areas of pavement on the site there's a little shed area that will be taken down otherwise the site has been pretty well cleared. Next slide so it's a very recent photo and there's just a few trees out there the site otherwise is pretty open there's a this access here will not be shared going forward and we're going to remove the pavement on Our side of that line. There's a new storm drain, water lane, water main, and sewer main all in Katahdin that also wraps around the corner that will be serving our project. Next slide. So the intent is to have a 15,000-square-foot, nearly square building in the third of the parcel. Two businesses will split the building this way. This always confuses people because that's the roof ridge line, But the building will be split this way, so we could have a smaller tenant could have access with an overhead door and some parking. Perhaps a larger tenant over here would have one depressed loading dock, one that grade. And then each one has some available area that's not necessarily intended for parking. We envision that the types of tenants that might come forward would be maybe a contractor that uses trailers, painting or plumbing company, maybe they've got some outdoor stuff, maybe they have some fleet vehicles that their employees would change out. So we've removed the parking there, and over here they're just going to be available for the contractor. Again, things might tweak a little bit as uses are identified each area. We have a little paver patio for employees to come out and enjoy it. We definitely see people utilizing the stark patio on a regular basis. Next slide, there it is, just overlaying on that photo so you can kind of see how it relates to everything. And next slide, so we'll have one large detention basin here. It'll be an under-drained soil filter. We will be seeding the bottom with a wildflower mix or something that would be like a rain garden-type plantings. We just collect our stormwater from each paved area and bring it around. This would come in here. We've gone over that with the DEP. This will be lined. That's just about everything in that area. We'll have a PVC liner, and that'll connect to the existing storm drain system, which comes down and will go out past the runways and on its way out. For your information, Chris, I show drip edges here, but they're not intended to be the BMPs. They're just basically splash guards with piping underneath to move the water away. We will have a sidewalk connection. It's going to come back into Stark. It's going to allow folks to come all the way out here and get onto the sidewalk system, maybe go to flight deck, go for their lunchtime walk as well. Right now we're proposing to add our sidewalk across the front and down here. We're going to be talking to the town about what might go beyond that particular interest. Next slide. This is probably hard to see out there. We've got better pictures. I made it worth you coming out tonight because we've got some pretty good art. But we will have some ornamental trees around the street line, the planting beds in front of the building, and some nice shade trees in the parking lot area and out back here for these nice folks. Next. So this is a conceptual perspective view from over the Katahdin and Pegasus sides. So you can see our stormwater basin is going to be full of lush vegetation, flowering and ornamental trees along the street, building plantings, probably daylilies over here since they can take just about anything with a combination of grasses and spirea I think I have out there out front. Next slide. Again, just giving an idea of how it's going to blend. And, of course, we will take our lawn areas all the way out to the edge of pavement, even though the right-of-way line is somewhat closer in. Next slide. This would be the street view of the front of the building. Next. So if you were driving to it from Pegasus, you'd get this street view. Next slide. And, again, this is the perspective view if you're coming at it from Admiral Fitch. You can see our new sidewalk. The sidewalk's out front. The plantings, both the dumpsters, of course, will be screened with vinyl slats and chain link fencing. We use pepper chrome for our renderings, and they obviously do a very nice job, but they forgot my tree here for that bench. Next, this will be coming out from the other side. We'll have a common sign and then signage for each business at the building. And one more. I think that's it. I'd be happy to address comments from the board.
[10:44] Speaker A (unidentified): Okay. Thank you, Kurt. Laura Hatmaker is here. Who would like to start? Chris?
[10:55] Speaker C (unidentified): Okay. I don't really have much on this. It seems like a nice project out there. I guess I'm a little surprised you're permitting it early ahead of time, but that's certainly up to you. It's a little speck, but that's fine. You met with the DEP and talked to them a little bit about it, so you're getting a site law permit. We did. And is it being considered a redevelopment project?
[11:21] Speaker B (unidentified): No, we're not going to use that, even though there's paved areas on site. Yeah. It just fits well. Yeah.
[11:29] Speaker C (unidentified): It was a little bit simpler. We'll have to provide full treatment, so that'll 95%. Wow. Wow, and it's site law, so you'll have to meet a flooding standard as well, 21025, so that's all good. The watershed is not Marybrook, correct? It goes out to the Androscoggin? Right.
[11:49] Speaker B (unidentified): I mean, technically, you might say the site is, but the drainage isn't, because it's going to connect to the storm drain line that goes out the other way.
[11:59] Speaker C (unidentified): Yeah, that's about it. Bike racks? We have bike racks. A couple of those on there. That's all I have. Okay. Looks like a good project. Laura?
[12:10] Speaker D (unidentified): I think the question of is if you're planning to excavate any. Oh, sorry. Sorry, I'll repeat myself. If there's any, the only question I would have is if there's any excavation being done, what's the plan for reuse of soils on site?
[12:27] Speaker B (unidentified): Yep, good question. We will keep all the soils on site. We can use them to lift the parking and building areas. There's not that much. So whatever we take out of the stormwater basin basically will be used right there on site.
[12:43] Speaker D (unidentified): Okay. And in terms of, like, containing any potential contaminants on site, what is your plan for that?
[12:50] Speaker B (unidentified): We'll submit the soils management plan with the final. But basically what we've been doing, if we had encountered something that was problematic, we would separate it and keep it on site. And but we don't envision that to be the case but we you know we can stockpile them off to the side and dispose of it either a beneficial use or something else we've been you know we did the start project and other projects right up there we've had a lot of conversations with people at the DEP Navy and EPA so we know their expectations and groundwater will probably be encountered. So we can, because it's a fairly small project, we could probably just get that over to the Navy's treatment facility. Otherwise we know the bigger train that was used at Stark as well. But yeah, we can submit any details, more descriptive plan with our final package.
[13:55] Speaker A (unidentified): And I'll add, and Matt can speak to this, But when Molneke came for final, we asked for a third-party reviewer on soil, and Matt can speak to that.
[14:13] Speaker E (unidentified): Yeah, if we do go with a third-party reviewer for this project, we've got some experience in managing that now with another recent project. And I have been receiving all of my reports from that reviewer and it's a I think it's a great way to keep track of everything a little extra work on our end but you know we'd rather be safe than
[14:40] Speaker D (unidentified): Sorry definitely and that will be something that I'll be interested to see on the final plan is what potential disposal would be if that's necessary thoughts for isolation of contaminants What are you going to do if you encountered groundwater to prevent potential new contaminants from entering into groundwater and things like that? Just kind of having those things teed up and ready to be answered. Absolutely.
[15:06] Speaker B (unidentified): And, Matt, I don't know if you got copied, but we finally received, I believe Monday, the permit for Priority Park or the buildings outside of Stark. The DEP also required the third-party inspector as part of that permit, and I'm sure they'll roll it in with this one. And if you haven't received that permit, I'd be happy to send a copy of it to you.
[15:30] Speaker E (unidentified): Yeah, I can't quite remember if I did or not, but I'll make sure to check.
[15:34] Speaker D (unidentified): Yeah, thank you. Otherwise, it looks like an awesome project. Good. Allison.
[15:44] Speaker F (unidentified): Sorry. Yeah, no, it looks like a great project. I'm really pleased with the approach to the exterior, at least conceptually, with the fenestration and the differentiation between the businesses that will be there. For fundamentally a warehouse, it's really attractive, and certainly the plantings, and I would have expected nothing less from this developer. And the rain garden or whatever, it's a great use of that space. I'm assuming you were you were in your cover letter you outlined a lot of the uses that were prohibited explicitly by the Navy, so I'm assuming that a lot of the fire marshal's concerns are covered by that. You couldn't have a social activity like a nightclub there anyway, so, you know, so that, and of course, you'll put in whatever fire suppression or whatever is required when you know your tenants, presumably. And the same, I assume, goes for the parking design, that it will be dependent on the tenant's needs. And obviously, if it changes in some way, you'll have to come back to staff and may come back to us eventually. [Speaker B (unidentified): Correct, yep.] I think that's all I had. I shared Laura's concerns about the media on site and how it was going to be handled with the problems we've had out there.
[17:23] Speaker G (unidentified): Okay. Steve. Sure, I don't have much to add. Thank you, Kurt. Good presentation, good project. The site location, you said the permit has now been granted, or you're working through that process?
[17:40] Speaker B (unidentified): No. The process that we've gone through with the DEP was Stark got its own stormwater permit. Yeah, okay. We modified that permit for the additional buildings. There's two online drive and 45,000 square foot. That was an amendment. Yeah. And at that point, we were just under 10 acres of total impervious area. And this one under common scheme kicks it all up. Sure, so, and you know it's a good time we for such an area. Yeah, conferred through the natural areas programs and historic districts and all like that. We'll get it all get it documented even though the land has basically been disturbed. And I think
[18:20] Speaker G (unidentified): folks can rest assured you've got that extra level of eyes up there looking at the soil and groundwater and everything else, right? So yeah, no, that's good. I drove past the other day and there's this is a odd question, but I drove past the other day and there's like four yellow like cement filled bollards sort of like east of the shed. What is that? Is that like an old test well or anything, or is that just remnant? I don't know. Sorry, Mr. Howard.
[18:56] Speaker A (unidentified): Those are a ballage left from the navy. That was a navy shed and they used it for storage.
[19:00] Speaker G (unidentified): We just haven't cleaned that site up and tore that shed down yet. Yeah, that'll all go away. Yeah, they're just upright and I wondered if they're guarding a wellhead or something, but anyway, no. Yeah, no, I don't have any further questions. Thank you. Thank you, Rob.
[19:17] Speaker A (unidentified): I think it's a great project and you know congratulate you in the design and
[19:24] Speaker F (unidentified): so forth and I think everything that I had questions about have been asked so
[19:28] Speaker A (unidentified): thank you. Okay, great. The only question I had was snow storage. Looks like it's It's creeping into the rain garden. Is that actually how it will be built?
[19:48] Speaker B (unidentified): It is, but we've got about 25 feet between the edge of pavement and the actual bed of the rain garden that does the heavy lifting. So any piles pushed off of the snow will be on the side slopes of that, not directly upon it. And obviously it's you know kind of hard to avoid doing it, but it was a similar idea at Stark where we have the long linear ones along the edge. If there's maintenance that has to be done to the stormwater BMP, well, you just have to do it, but we've tried to keep it so that the actual soil filtering part is moved as far away from any plowed areas as possible. Okay, good. Any other
Unfinished Business
[20:35] Speaker A (unidentified): there are comments or questions? I don't see anybody online unless Jim Howard wants to ask a question or make a comment. There's nobody in the audience. I'll close any public comment we might have had and I'd like a motion that the sketch plan application is approved. Do I have a motion? Motion by Laura, second by Allison. All those in favor? That's unanimous of the board members present. All right. Thank you very much. We'll see you soon for final. Thank you. Any other business, old business, new business comments? Okay. We meet in two weeks. Laura will not be here. Safe travels. Happy Thanksgiving. The rest of us will be here on Tuesday. God willing, the creek don't rise.
[21:48] Speaker E (unidentified): We may or may not actually have anything on the agenda for that meeting, but if we do, it would likely just be one item again. Okay. But I'm considering, whether or not we'll be going to, a December meeting instead, depends on how the applicant would like to proceed. Okay. If you'd like to know more, you can always watch the SRC from today. Okay.
[22:14] Speaker G (unidentified): So is this just a slowdown in applicants or is it just the odd timing of?
[22:19] Speaker E (unidentified): We have not gotten a lot of applicants, lately. They tend to come in batches and we don't have very many right now. We have one contract zone that's going through but it is kind of ballooning with additional reviews like street standards waivers and planning board review on top of the contract zoning so that is just slowing down that process for that applicant slightly potentially. Otherwise we just don't have any the applicants that are ready to proceed at this time.
[22:55] Speaker F (unidentified): Matt, just so you know, I'm going to miss, if there's a second December meeting, I would miss that if there even is one. I was
[23:03] Speaker E (unidentified): planning on not scheduling one if we can help it, just with these two holidays and the meetings being the same week. I'm looking to both make sure that staff is available and planning board members as well as the public because I don't want to do a disservice to anybody by not giving ample time for people to review things.
[23:26] Speaker A (unidentified): Yeah, and we have in the past...
[23:29] Speaker F (unidentified): Right, I remember we often don't have a second one.
[23:31] Speaker A (unidentified):...canceled the meeting closest to Christmas. Okay, any other comments? We are adjourned, 625. Jim, I think that could be our record.
[23:42] Speaker F (unidentified): My half-hour parking spot is okay.